DEN Discussion List Archive
[Date Prev][Date Next][Date Index]
[Thread Index]
[Author Index]
RE: Periodic Control Charts
- Subject: RE: Periodic Control Charts
- From: "Dr. W. J. Latzko" <latzko@att.net>
- Date: Thu, 21 Mar 2002 10:22:45 -0500
At 04:28 PM 3/19/2002 +0530, you wrote:
>In x-bar and R charts, we control the process average and range. In this
>example probably, it could be appropriate to control the weekly
>consumption rather than average/ day.
What is suggested here is possible. However, from the description of the
problem, most likely it will increase the variance. One will measure the
total variation which is composed of the variance between the days plus the
variance within the days. In short, the subsample will be heterogeneous and
so would not fit the "rational subsample" concept of Shewhart.
Bill
Latzko@att.net
DEN Home |
Main Index |
Thread Index |
Author Index